Question : P alone can complete a work in 15 days and Q alone can complete the same work in 12 days. They start the work together but after 3 days P leaves the work. How much time will Q take to finish the remaining work?

Option 1: 7.2 days

Option 2: 7.8 days

Option 3: 8.5 days

Option 4: 6.6 days


Team Careers360 24th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 6.6 days


Solution : P alone can complete a work in 15 days.
⇒ P's 1 day's work = $\frac{1}{15}$
Q alone can complete the same work in 12 days.
⇒ Q's 1 day's work = $\frac{1}{12}$
So, (P + Q)'s 1 day's work = $\frac{1}{15}+\frac{1}{12}=\frac{3}{20}$
⇒ (P + Q)'s 3 days work = $\frac{3}{20}×3=\frac{9}{20}$
Remaining work $=1-\frac{9}{20}=\frac{11}{20}$
So, Q's will complete the remaining work in $\frac{\frac{11}{20}}{\frac{1}{12}}=\frac{33}{5}=6.6$ days
Hence, the correct answer is 6.6 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books