11 Views

Question : P and Q can do a work together in 30 days. Q and R can do the same work together in 24 days and R and P together in 20 days. They started the work together, but Q and R left after 10 days. How many more days will P take to finish the remaining work?

Option 1: 23

Option 2: 21

Option 3: 18

Option 4: 19


Team Careers360 22nd Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 18


Solution : LCM of 30, 24 and 20 = 120
Total work = 120 units
Efficiency of (P + Q) = $\frac{120}{30}=4$ units/day
Efficiency of (Q + R) = $\frac{120}{24}=5$ units/day
Efficiency of (R + P) = $\frac{120}{20}=6$ units/day
Now, (P + Q) + (Q + R) + (R + P) = 4 + 5 + 6
⇒ 2 (P + Q + R) = 15
⇒ (P + Q + R) = $\frac{15}{2}$units/day
One day work of (P + Q + R) = $\frac{15}{2}$
Ten day work of (P + Q + R) = $\frac{15}{2}\times10=75$
Remaining work = 120 – 75 = 45
Efficiency of P = efficiency of (P + Q + R) – efficiency of (Q + R) = $\frac{15}{2}-5$ = $\frac{5}{2}$
The remaining work done by P with an efficiency of $\frac{5}{2}$ = $\frac{45}{\frac{5}{2}}$ = 18
Hence, the correct answer is 18.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books