Question : P and Q together can do a work in 12 days. P alone can do the same work in 36 days. In how many days can Q alone complete two-thirds part of the same work?
Option 1: 12
Option 2: 15
Option 3: 18
Option 4: 21
Correct Answer: 12
Solution : Time taken by P and Q to do the work = 12 days (P and Q)'s 1 day's work = $\frac{1}{12}$ P alone can do the work in 36 days P's 1 day's work = $\frac{1}{36}$ Q's 1 day's work = $\frac{1}{12} - \frac{1}{36}=\frac{2}{36}=\frac{1}{18}$ ⇒ Q can do the whole work in 18 days So, $\frac{2}{3}$ work can be done by Q in 18 × ($\frac{2}{3}$) = 12 days Hence, the correct answer is 12.
Result | Eligibility | Application | Selection Process | Cutoff | Admit Card | Preparation Tips
Question : P and Q together can do a work in 12 days. P alone can do the same work in 18 days. In how many days can Q alone complete two-thirds part of the same work?
Question : P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
Question : A and B can do a piece of work in 25 days. B alone can do $66 \frac{2}{3}$% of the same work in 30 days. In how many days can A alone do $\frac{4}{15}$th part of the same work?
Question : P and Q can do a work together in 30 days. Q and R can do the same work together in 24 days and R and P together in 20 days. They started the work together, but Q and R left after 10 days. How many more days will P take to finish the remaining work?
Question : A can do $\frac{4}{5}$th of a work in 20 days and B can do $\frac{3}{4}$th of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete $\frac{3}{4}$th of the same work in:
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile