34 Views

Question : P and Q together complete a job in $4 \frac{2}{5}$ days. R and S complete the same job in $4 \frac{8}{9}$ days. If P, Q, R, and S work together, how many days do they need to complete the same job?

Option 1: $2 \frac{7}{18}$

Option 2: $1 \frac{7}{18}$

Option 3: $1 \frac{6}{19}$

Option 4: $2 \frac{6}{19}$


Team Careers360 2nd Jan, 2024
Answer (1)
Team Careers360 9th Jan, 2024

Correct Answer: $2 \frac{6}{19}$


Solution : P and Q complete the job in $4 \frac{2}{5}$ days = $\frac{22}{5}$ days
R and S complete the same job in $4 \frac{8}{9}$ days = $\frac{44}{9}$ days
P, Q, R, and S, working together, would complete in 1 day $=\frac{5}{22}+ \frac{9}{44} = \frac{10+9}{44} = \frac{19}{44}$th of the job.
$\therefore$ P, Q, R, and S would complete the entire job in $\frac{44}{19} = 2\frac{6}{19}$ days
Hence, the correct answer is $2\frac{6}{19}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books