Question : P can finish a work in 18 days. When he had worked for 5 days, Q joined him. If both of them together completed the remaining work in $\frac{13}{5}$ days, then in how many days can Q alone finish $66 \frac{2}{3}\%$ of the same work?
Option 1: 5
Option 2: 4
Option 3: 2
Option 4: 3
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: 3
Solution : Let the total work be 18 units. So, the efficiency of P = $\frac{18}{18}$ = 1 Now, work done by P in 5 days = (1 × 5) = 5 units The remaining work = (18 – 5) = 13 units So, 13 units of work done by P and Q in $\frac{13}{5}$ days, Now, the total efficiency of P and Q = $13\ ÷\ \frac{13}{5}$ = 5 So, the efficiency of Q = (5 – 1) = 4 Also, $66\frac{2}{3}\%$ of total work = $\frac{2}{3}$rd of the total work = $\frac{2}{3}$ × 18 = 12 units So, the required days for Q alone to do the 12 units of work = $\frac{12}{4}$ = 3 days Hence, the correct answer is 3.
Candidates can download this ebook to know all about SSC CGL.
Admit Card | Eligibility | Application | Selection Process | Preparation Tips | Result | Answer Key
Question : P, Q, and R can complete a piece of work in 10 days, 15 days, and 20 days, respectively. If they work together, in how many days can they finish the same work?
Question : A can do $\frac{1}{3}$rd of a piece of work in 32 days, B can do $37 \frac{1}{2}$% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left and A joined C and together, completed the
Question : A and B together can finish a work in 30 days. They worked on it for 20 days and then B left. The remaining work was done by A alone in 20 days. In how many days can A alone finish the work?
Question : Sara can finish a work in 18 days and Tara can complete the same work in 15 days. Tara worked for 10 days and left the job. In how many days can Sara finish the remaining work alone?
Question : P, Q, and R can finish a work in 5 days, 10 days, and 15 days, respectively, working alone. P and Q work on the first day, P and R work on the second day, P and Q work on the third day and so on till the work is completed. In how many days the work will be completed?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile