P is twice as fast as Q and R together .Working together ,all three can do a work in 21 days.In how many days can Q and R together do the work


Simran 9th Jan, 2020
Answer (1)
KUNAL LANJEWAR 14th Jan, 2020

Hello,

Let, the work done by P be p

and the work done by Q and R together be x

So, from first condition, p = 2x

All three can do work in 21 days.

So, 21 [ ( 1 / 2x ) + ( 1 / x ) ] = 1

So, 21 ( 3x / 2 x^2 ) = 1

So, 2x = 3 x 21

So, x = 63 / 2

So, x = 31.5 days.

So, Q and R can do the work together in 31.5 days

Best Wishes.

Related Questions

UPES Integrated LLB Admission...
Apply
Ranked #28 amongst Institutions in India by NIRF | Ranked #1 in India for Academic Reputation by QS University Rankings | 16.6 LPA Highest CTC
Jindal Global Law School Admi...
Apply
Ranked #1 Law School in India & South Asia by QS- World University Rankings | Merit cum means scholarships | Application Deadline: 30th Nov'24
Chandigarh University Admissi...
Apply
Ranked #1 Among all Private Indian Universities In QS Asia Rankings 2025 | Scholarships worth 210 CR
Great Lakes PGPM & PGDM 2025
Apply
Admissions Open | Globally Recognized by AACSB (US) & AMBA (UK) | 17.3 LPA Avg. CTC for PGPM 2024 | Application Deadline: 1st Dec 2024
ICFAI Business School-IBSAT 2024
Apply
9 IBS Campuses | Scholarships Worth Rs 10 CR
Nirma University Law Admissio...
Apply
Grade 'A+' accredited by NAAC
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books