6 Views

Question : P, Q, and R alone can do a piece of work in 5, 6, and 4 days, respectively. All three of them began the work together but Q left 1 day before completion of the work. In how many days was the work completed?

Option 1: $\frac{70}{37}$ days

Option 2: $\frac{100}{27}$ days

Option 3: $3$ days

Option 4: $\frac{80}{23}$ days


Team Careers360 8th Jan, 2024
Answer (1)
Team Careers360 15th Jan, 2024

Correct Answer: $\frac{70}{37}$ days


Solution : Let the total number of days be t.
Rate of P = $\frac{1}{5}$​ per day
Rate of Q = $\frac{1}{6}$ per day
Rate of R = $\frac{1}{4}$ per day
⇒ Combined rate = $\frac{1}{5}$ + $\frac{1}{6}$ + $\frac{1}{4}$ = $\frac{12}{60}$ + $\frac{10}{60}$ + $\frac{15}{60}$ = $\frac{37}{60}$
Q leaves 1 day before the completion of the work.
So, P, Q, and R worked together for (t – 1) days, and P and R worked on the last day.
Total work = 1 = $\frac{37}{60}$ × (t – 1) + $\frac{9}{20}$
⇒ 1 – $\frac{9}{20}$ = $\frac{37}{60}$ × (t – 1)
⇒ $\frac{11}{20}$ = $\frac{37}{60}$ × (t – 1)
⇒ $\frac{11×60}{20×37}$ = (t – 1)
⇒ $\frac{33}{37}$ + 1 = t
⇒ t = $\frac{70}{37}$
Hence, the correct answer is $\frac{70}{37}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books