5 Views

Question : P, Q, and R alone can do a piece of work in 5, 6, and 4 days, respectively. All three of them began the work together but Q left 1 day before completion of the work. In how many days was the work completed?

Option 1: $\frac{70}{37}$ days

Option 2: $\frac{100}{27}$ days

Option 3: $3$ days

Option 4: $\frac{80}{23}$ days


Team Careers360 8th Jan, 2024
Answer (1)
Team Careers360 15th Jan, 2024

Correct Answer: $\frac{70}{37}$ days


Solution : Let the total number of days be t.
Rate of P = $\frac{1}{5}$​ per day
Rate of Q = $\frac{1}{6}$ per day
Rate of R = $\frac{1}{4}$ per day
⇒ Combined rate = $\frac{1}{5}$ + $\frac{1}{6}$ + $\frac{1}{4}$ = $\frac{12}{60}$ + $\frac{10}{60}$ + $\frac{15}{60}$ = $\frac{37}{60}$
Q leaves 1 day before the completion of the work.
So, P, Q, and R worked together for (t – 1) days, and P and R worked on the last day.
Total work = 1 = $\frac{37}{60}$ × (t – 1) + $\frac{9}{20}$
⇒ 1 – $\frac{9}{20}$ = $\frac{37}{60}$ × (t – 1)
⇒ $\frac{11}{20}$ = $\frac{37}{60}$ × (t – 1)
⇒ $\frac{11×60}{20×37}$ = (t – 1)
⇒ $\frac{33}{37}$ + 1 = t
⇒ t = $\frac{70}{37}$
Hence, the correct answer is $\frac{70}{37}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books