1 View

Question : P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?

Option 1: 40 days

Option 2: 72 days

Option 3: 84 days

Option 4: 90 days


Team Careers360 21st Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 72 days


Solution : Given: P, Q, and R together can complete a work in 40 days and P and Q together can complete the same in 90 days.
Total work = Efficiency × Time
Total work is LCM of (40, 90) = 360 units
Efficiency of (P + Q + R) is $\frac{360}{40}$ = 9
Efficiency of (P + Q) is $\frac{360}{90}$ = 4
Then, the efficiency of R = [Efficiency of (P + Q + R) – Efficiency of (P + Q)] = 9 – 4 = 5
So, the time taken by R is given using the formula, $\frac{\text{work}}{\text{efficiency}}$ = $\frac{360}{5}$ = 72 days
Hence, the correct answer is 72 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books