Question : P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
Option 1: 40 days
Option 2: 72 days
Option 3: 84 days
Option 4: 90 days
Correct Answer: 72 days
Solution : Given: P, Q, and R together can complete a work in 40 days and P and Q together can complete the same in 90 days. Total work = Efficiency × Time Total work is LCM of (40, 90) = 360 units Efficiency of (P + Q + R) is $\frac{360}{40}$ = 9 Efficiency of (P + Q) is $\frac{360}{90}$ = 4 Then, the efficiency of R = [Efficiency of (P + Q + R) – Efficiency of (P + Q)] = 9 – 4 = 5 So, the time taken by R is given using the formula, $\frac{\text{work}}{\text{efficiency}}$ = $\frac{360}{5}$ = 72 days Hence, the correct answer is 72 days.
Result | Eligibility | Application | Selection Process | Cutoff | Admit Card | Preparation Tips
Question : A, B and C together can complete a work in 20 days. A and B together can complete the same work in 30 days. Then, C alone can complete the same work in how many days?
Question : P and Q together can do a work in 12 days. P alone can do the same work in 18 days. In how many days can Q alone complete two-thirds part of the same work?
Question : P and Q together can do a work in 12 days. P alone can do the same work in 36 days. In how many days can Q alone complete two-thirds part of the same work?
Question : P and Q can do a piece of work in 14 days. Q and R together can do it in 21 days. If P is twice as good a workman as R, then in how many days Q alone can do the work?
Question : Vijay and Sahil together complete a piece of work in 40 days, Sahil and Ranjit can complete the same work in 48 days and Ranjit and Vijay can complete the same in 60 days. In how many days can all three complete the same work while working together?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile