1 View

Question : P, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?

Option 1: 40 days

Option 2: 72 days

Option 3: 84 days

Option 4: 90 days


Team Careers360 21st Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 72 days


Solution : Given: P, Q, and R together can complete a work in 40 days and P and Q together can complete the same in 90 days.
Total work = Efficiency × Time
Total work is LCM of (40, 90) = 360 units
Efficiency of (P + Q + R) is $\frac{360}{40}$ = 9
Efficiency of (P + Q) is $\frac{360}{90}$ = 4
Then, the efficiency of R = [Efficiency of (P + Q + R) – Efficiency of (P + Q)] = 9 – 4 = 5
So, the time taken by R is given using the formula, $\frac{\text{work}}{\text{efficiency}}$ = $\frac{360}{5}$ = 72 days
Hence, the correct answer is 72 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books