121 Views

Question : P, Q, and R, when working individually, can complete a job in, respectively, 36 days, 48 days, and 144 days. P, Q, and R start working together. P leaves the job 12 days before completion and Q leaves the job 8 days before completion. R works from the beginning till the end of the job. Determine the total number of days taken to complete the job.

Option 1: 24

Option 2: 27

Option 3: 30

Option 4: 25


Team Careers360 22nd Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 27


Solution : Let the total work = LCM (36, 48, and 144) = 144
According to the question,
Efficiency of P = $\frac{144}{36}$ = 4
Efficiency of Q = $\frac{144}{48}$ = 3
Efficiency of R = $\frac{144}{144}$ = 1
Additional work P could have done if not left = 4 × 12 = 48
Additional work Q could have done if not left = 3 × 8 = 24
Now,
Effective total work = 144 + 48 + 24 = 216
$\therefore$ Time taken = $\frac{\text{Total work}}{\text{Efficiency}}$ = $\frac{216}{8}$ = 27 days
Hence, the correct answer is 27.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books