225 Views

Question : P, Q, and R, when working individually, can complete a job in, respectively, 36 days, 48 days, and 144 days. P, Q, and R start working together. P leaves the job 12 days before completion and Q leaves the job 8 days before completion. R works from the beginning till the end of the job. Determine the total number of days taken to complete the job.

Option 1: 24

Option 2: 27

Option 3: 30

Option 4: 25


Team Careers360 22nd Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 27


Solution : Let the total work = LCM (36, 48, and 144) = 144
According to the question,
Efficiency of P = $\frac{144}{36}$ = 4
Efficiency of Q = $\frac{144}{48}$ = 3
Efficiency of R = $\frac{144}{144}$ = 1
Additional work P could have done if not left = 4 × 12 = 48
Additional work Q could have done if not left = 3 × 8 = 24
Now,
Effective total work = 144 + 48 + 24 = 216
$\therefore$ Time taken = $\frac{\text{Total work}}{\text{Efficiency}}$ = $\frac{216}{8}$ = 27 days
Hence, the correct answer is 27.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books