Question : R, S, and T can finish a work in 20,15, and 10 days, respectively. R works on all days and S and T work on alternate days with T starting the work on the first day. In how many days is the work finished?

Option 1: $\frac{61}{7}$

Option 2: $\frac{50}{7}$

Option 3: $\frac{52}{7}$

Option 4: $\frac{57}{8}$


Team Careers360 17th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: $\frac{52}{7}$


Solution : Given: R alone can complete a task in 20 days.
T alone can complete the same task in 15 days.
S alone can complete the same task in 10 days.
Total work is LCM of 20,15 and 10 = 60 units
So, the efficiency of R  $=\frac{60}{20} = 3$ units per day
Efficiency of S $=\frac{60}{15} = 4$ units per day
Efficiency of T $=\frac{60}{10} = 6$ units per day
R works on all days, and S and T work on alternate days, starting with T.
So, work done in 2 days = ((efficiency of (R + T)) × 1days) + ((efficiency of (R + S)) × 1 days).
= ((3 + 6) × 1days) + ((3 + 4) × 1 days) = 16 units.
Work done in 2 days = 16 units.
So, work done in 6 days = 48 units.
Work left = 12 units.
Now (R + T) start again and do 9 units of work on the 7th day.
So, their 7 days of work is 57 units.
Work left now is 3 units.
Now, (R + S) start and do 7 units of work in 1 day.
So (R + S) do 3 units of work in $\frac{3}{7}$ days.
So, the total time taken is 7 days + $\frac{3}{7}$ days = $\frac{52}{7}$ days
Hence, the correct answer is $\frac{52}{7}$.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books