Question : Rahul alone can complete a work in 10 days and Sonu alone can complete the same work in 15 days. If they work together for 4 days, then what part of total work is left?

Option 1: $\frac{2}{3}$

Option 2: $\frac{1}{5}$

Option 3: $\frac{1}{3}$

Option 4: $\frac{2}{5}$


Team Careers360 11th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: $\frac{1}{3}$


Solution : Time taken by Rahul to complete the work = 10 days
Time taken by Sonu to complete the work = 15 days
Let the total work = LCM of 18 and 15 = 90 units
Efficiency of Rahul = $\frac{90}{10}$ = 9 units/day
Efficiency of Sonu = $\frac{90}{15}$ = 6 units/day
Total Efficiency of Rahul and Sonu = 9 + 6 = 15 units/day
Work was completed by them in 4 days = 15 × 4 = 60 units
Remaining work = 90 – 60 = 30 units
Remaining part of the work left = $\frac{30}{90}$ = $\frac{1}{3}$
Hence, the correct answer is $\frac{1}{3}$.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books