Question : Rahul alone can complete a work in 10 days and Sonu alone can complete the same work in 15 days. If they work together for 4 days, then what part of total work is left?

Option 1: $\frac{2}{3}$

Option 2: $\frac{1}{5}$

Option 3: $\frac{1}{3}$

Option 4: $\frac{2}{5}$


Team Careers360 11th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: $\frac{1}{3}$


Solution : Time taken by Rahul to complete the work = 10 days
Time taken by Sonu to complete the work = 15 days
Let the total work = LCM of 18 and 15 = 90 units
Efficiency of Rahul = $\frac{90}{10}$ = 9 units/day
Efficiency of Sonu = $\frac{90}{15}$ = 6 units/day
Total Efficiency of Rahul and Sonu = 9 + 6 = 15 units/day
Work was completed by them in 4 days = 15 × 4 = 60 units
Remaining work = 90 – 60 = 30 units
Remaining part of the work left = $\frac{30}{90}$ = $\frac{1}{3}$
Hence, the correct answer is $\frac{1}{3}$.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books