Question : Ram can complete a task in 15 days, Rohan in 25 days, and Rohit in 30 days. Rohan and Rohit worked together for 2 days and then, Rohit was replaced by Ram. In how many days altogether was the work completed?

Option 1: 10 days

Option 2: 8 days

Option 3: 12 days

Option 4: 7 days


Team Careers360 2nd Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: 10 days


Solution : Given:
Ram can complete a task in 15 days, Rohan in 25 days, and Rohit in 30 days.
Work done by Ram in 1 day $= \frac{1}{15}$
Work done by Rohan in 1 day $= \frac{1}{25}$
Work done by Rohit in 1 day $=\frac{1}{30}$
Rohan and Rohit worked together for 2 days.
Work done by (Rohan + Rohit) in 1 day $= \frac{1}{25}+\frac{1}{30}=\frac{11}{150}$
Work done by them in 2 days $= 2×\frac{11}{150}=\frac{11}{75}$
Work left = $1-\frac{11}{75}=\frac{64}{75}$
Then, Rohit was replaced by Ram.
Work done by (Rohan + Ram) in 1 day $= \frac{1}{25}+\frac{1}{15}=\frac{8}{75}$
So, the remaining work will take $\frac{\frac{64}{75}}{\frac{8}{75}}=8$ days
So, the total work will take (8 + 2) = 10 days
Hence, the correct answer is 10 days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books