Question : Ramesh alone can complete a work in 24 days. Ramesh and Somesh can complete it in 8 days. How long will Somesh alone take to complete the work?
Option 1: 10 days
Option 2: 15 days
Option 3: 14 days
Option 4: 12 days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 12 days
Solution : Time taken by Ramesh and Somesh to complete the work = 8 days ⇒ Part of work done by Ramesh and Somesh together in a day = $\frac{1}{8}$ Time taken by Ramesh alone to complete the work = 24 days ⇒ Part of work done by Ramesh alone in a day = $\frac{1}{24}$ Let the time taken by Somesh alone to complete the work = $x$ days ⇒ Part of work done by Somesh alone in a day = $\frac{1}{x}$ ⇒ $\frac{1}{24} + \frac{1}{x} = \frac{1}{8}$ ⇒ $\frac{1}{x} = \frac{1}{8}–\frac{1}{24} = \frac{3–1}{24} = \frac{1}{12}$ ⇒ Time taken by Somesh alone to complete the work = 12 days Hence, the correct answer is 12 days.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : Ram and Ramesh can do work in 12 days, Ramesh and Somesh in 15 days and Somesh and Ram in 10 days. If Ram, Ramesh, and Somesh work together, in how many days will they complete the work?
Question : A can complete a piece of work in 14 days, while A and B together can complete it in $3\frac{1}{2}$ days. How long will B alone take to complete it?
Question : A can complete a work in 18 days, while B can complete it in 12 days. B worked on it for 4 days. How long will A take to finish the remaining work?
Question : Anshu, Swati, and Rajni can finish a work in 4 days if they work together. However, Anshu alone will take 9 days to complete the work, and Swati alone will complete the work in 12 days. How many days will Rajni alone take to complete the work?
Question : 12 men and 12 women can complete a piece of work in 9 days. 6 men and 15 women can complete the same work in 12 days. How long (in days) would it take 9 women to complete half the work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile