Question : Reshma alone can do a work in 14 days. Bhavana is 40% more efficient than Reshma. The number of days, Bhavana alone will take to do the same piece of work is:

Option 1: 10 days

Option 2: 40 days

Option 3: 28 days

Option 4: 14 days


Team Careers360 17th Jan, 2024
Answer (1)
Team Careers360 19th Jan, 2024

Correct Answer: 10 days


Solution : Let the time Bhavana takes to complete the work as B.
Since Bhavana is 40% more efficient than Reshma,
she can complete the work in $\frac{100\%}{140\%}$ = $\frac{5}{7}$th of the time that Reshma takes.
⇒ B = $\frac{5}{7} × 14$
⇒ B = $10$
Hence, the correct answer is 10 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books