Question : Rohan alone can do a work in 10 days and Mohan alone can do the same work in 15 days. In how many days will they together complete the same work?
Option 1: 6 days
Option 2: 5 days
Option 3: 4 days
Option 4: 7 days
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 6 days
Solution : Time taken by Rohan to do the work = 10 days Part of work done by Rohan in a day = $\frac{1}{10}$ Time taken by Mohan to do the work = 15 days Part of work done by Rohan in a day = $\frac{1}{15}$ Part of the work done by Rohan and Mohan in a day = $\frac{1}{10}$ + $\frac{1}{15}$ = $\frac{3+2}{30}$ = $\frac{1}{6}$ Time taken by Rohan and Mohan to do the work = 6 days Hence, the correct answer is 6 days.
Answer Key | Cutoff | Selection Process | Preparation Tips | Eligibility | Application | Exam Pattern
Question : A and B together can complete a given work in 10 days. C can complete the same work alone in 15 days. In how many days can they complete the work, if all three work together?
Question : Seema alone can do a piece of work in 8 days and her sister Reema alone can do the same work in 24 days. If they worked together, then in how many days they will complete the work?
Question : A, B, and C together can complete a work in 5 days. A and B together can complete the same work in 6 days. C alone can finish the same work in how many days?
Question : Akbar can complete a piece of work alone in 12 days, while Anthony can complete the same work alone in 20 days. If they work on alternate days with Anthony starting the work, then in how many days can they complete the whole work?
Question : A alone can do a work in 4 days, which B alone can do in 6 days. In how many days they together can do it?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile