Question : Ruchi, Khushi, and Teju can do a piece of work in 30, 40, and 60 days respectively. In how many days can Ruchi do the work, if she is assisted by both Khushi and Teju on every third day?

Option 1: $\frac{550}{12}$

Option 2: $\frac{85}{4}$

Option 3: $\frac{71}{2}$

Option 4: $\frac{360}{17}$


Team Careers360 5th Jan, 2024
Answer (1)
Team Careers360 8th Jan, 2024

Correct Answer: $\frac{85}{4}$


Solution : Let the total work be 120 units.
As LCM of 30, 40 and 60 is 120 units.
The efficiency of Ruchi, Khushi and Teju = 4, 3, 2
In 3 days, the total work complete = 4 + 4 + 9 = 17 units of work
In 21 days, the total work completed = 17 × 7 = 119 units of work
The remaining 1 unit will be completed by Ruchi in $\frac{1}{4}$ days.
$\therefore$ The total time = 21 + $\frac{1}{4}$ = $\frac{85}{4}$ days
Hence, the correct answer is $\frac{85}{4}$.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books