Rudra Sanjay and tiger can complete a piece of work in 48 days 60 days and 72 days respectively they started the work together but after 9 days Tiger left if the Sanju live 6 days before the completing of the work in how many days will the work be completed


Simran 27th Mar, 2020
Answer (1)
Sai Sri Nandan Ch 27th Mar, 2020

Hello,

Let the work done by Rudra, Sanjay and Tiger in one day individually be x,y,z respectively.

Therefore, from question, 48x = 60y = 72z.   Let this be equation ((1)).

For initial 9 days, work done is 9(x+y+z).

Next 6 days, work done is 6(x+y).

The rest of the days, say M days, work done is M * x.

Adding all these, we get, (M+9+6)x + (9+6)y + 9z.

By using equation 1, convert this into only "x" terms.

Thus we get, (M+9+6+11.2+6)x. This work is equal to the total work, i.e 48x.

Thus, solving for M, we get, (M+32.2)x=48x

M=15.8. Rounded off, we get M = 16 days.

Therefore total days required is 16+9+6= 31 days.

Hope this helps.

Comment for clarification.

Thanks.

Related Questions

MAHE Manipal M.Tech 2025
Apply
NAAC A++ Accredited | Accorded institution of Eminence by Govt. of India | NIRF Rank #4
Amity University, Noida Law A...
Apply
700+ Campus placements at top national and global law firms, corporates, and judiciaries
Amity University, Noida BBA A...
Apply
Ranked amongst top 3% universities globally (QS Rankings)
UPES | BBA Admissions 2025
Apply
#41 in NIRF, NAAC ‘A’ Grade | 100% Placement, up to 30% meritorious scholarships | Last Date to Apply: 28th Feb
Chandigarh University Admissi...
Apply
Ranked #1 Among all Private Indian Universities in QS Asia Rankings 2025 | Scholarships worth 210 CR
Sanskriti University LLM Admi...
Apply
Best innovation and research-driven university of Uttar Pradesh
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books