Question : S does half as much work as T in $\frac{1}{8}$th of the time taken by T. If they together complete a work in 60 days, then how many days shall S alone take to complete that work?
Option 1: 100 days
Option 2: 80 days
Option 3: 90 days
Option 4: 75 days
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 75 days
Solution : Let the time T takes to complete the work = $x$ days ⇒ the time T takes to complete half of the work = $\frac{x}{2}$ days ⇒ So, S will take to complete half of the work = $\frac{1}{8x}$ So, $\frac{\text{Efficiecncy of T}}{\text{Efficiency of S}}=\frac{\text{Time taken by S}}{\text{Time taken by T}}$ = $\frac{\frac{1}{8x}}{\frac{x}2}$ = $\frac{1}{4}$ Together they complete the work in 60 days, ⇒ Total work = 60 × (1 + 4) = 300 units S will take to finish the whole work = $\frac{300}4$ = 75 days Hence, the correct answer is 75 days.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : Rahul alone can complete a work in 10 days and Sonu alone can complete the same work in 15 days. If they work together for 4 days, then what part of total work is left?
Question : P, Q, and R can complete a work alone in 12,15, and 20 days respectively. They started the work together. P left the work 8 days before the work was completed and Q left the work 5 days after P had left. R completed the remaining work alone. How many days will be required to
Question : Babita is 1.25 times as efficient as Deepak. Working together, they can complete a piece of work in 40 days. In how many days can Deepak alone complete the same piece of work?
Question : A and B together can complete a piece of work in 15 days and B alone can complete it in 21 days. In how many days can A complete it alone?
Question : The ratio of time taken to complete a work by a man and a woman is 2 : 3. The man and the woman can complete the work together in 24 days. In how many days can the woman complete the work alone?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile