20 Views

Question : Sanjay and Rohan can complete a work in 8 days and 12 days, respectively. Starting with Sanjay, they work on alternate days. In how many days will the work be completed?

Option 1: $8 \frac{1}{2}$

Option 2: $9 \frac{1}{2}$

Option 3: $9 \frac{2}{3}$

Option 4: $9 \frac{1}{3}$


Team Careers360 22nd Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: $9 \frac{1}{2}$


Solution : Time taken by Sanjay to complete the work = 8 days
Part of work done by Sanjay in a day = $\frac{1}{8}$
Time taken by Rohan to complete the work = 12 days
Part of work done by Rohan in a day = $\frac{1}{12}$
Part of the work done by Sanjay and Rohan in two days
= $\frac{1}{8}+\frac{1}{12}$
= $\frac{3+2}{24}$
= $\frac{5}{24}$
Part of the work done by Sanjay and Rohan in 8 days = $\frac{5×4}{24} = \frac{20}{24}$
Part of the work done by Sanjay in 9th day = $\frac{1}{8} = \frac{3}{24}$
Remaining work = $\frac{24-20-3}{24} = \frac{1}{24}$
Time taken by Rohan to complete the remaining work = $\frac{\frac{1}{24}}{\frac{1}{12}} = \frac{1}{2}$ day
Total time taken = $9+\frac{1}{2}= 9\frac{1}{2}$ days
Hence, the correct answer is $9\frac{1}{2}$.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books