Question : Suresh alone can do work in 10 days working 1 hour a day. Balu alone can do the same work in 2 days working 5 hours a day. How many hours do they need to work together in a day to complete the same work in 10 days?

Option 1: 1.5 hours

Option 2: 0.5 hours

Option 3: 1 hour

Option 4: 2 hours


Team Careers360 14th Jan, 2024
Answer (1)
Team Careers360 18th Jan, 2024

Correct Answer: 0.5 hours


Solution : Total time taken by Suresh to do the work = 10 × 1 = 10 hours
⇒ Part of the work done by Suresh in an hour = $\frac{1}{10}$
Total time taken by Balu to do the work = 5 × 2 = 10 hours
⇒ Part of the work done by Balu in an hour = $\frac{1}{10}$
So, part of the work done by Suresh and Balu together in a day = $\frac{1}{10}$ + $\frac{1}{10}$ = $\frac{1+1}{10}$ = $\frac{1}{5}$
$\therefore$ Total time Suresh and Balu took to do the work = $\frac{1}{\frac{1}{5}}=5$ hours = 0.5 hours per day for 10 days
Hence, the correct answer is 0.5 hours.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books