29 Views

Question : Suresh alone can do work in 10 days working 1 hour a day. Balu alone can do the same work in 2 days working 5 hours a day. How many hours do they need to work together in a day to complete the same work in 10 days?

Option 1: 1.5 hours

Option 2: 0.5 hours

Option 3: 1 hour

Option 4: 2 hours


Team Careers360 14th Jan, 2024
Answer (1)
Team Careers360 18th Jan, 2024

Correct Answer: 0.5 hours


Solution : Total time taken by Suresh to do the work = 10 × 1 = 10 hours
⇒ Part of the work done by Suresh in an hour = $\frac{1}{10}$
Total time taken by Balu to do the work = 5 × 2 = 10 hours
⇒ Part of the work done by Balu in an hour = $\frac{1}{10}$
So, part of the work done by Suresh and Balu together in a day = $\frac{1}{10}$ + $\frac{1}{10}$ = $\frac{1+1}{10}$ = $\frac{1}{5}$
$\therefore$ Total time Suresh and Balu took to do the work = $\frac{1}{\frac{1}{5}}=5$ hours = 0.5 hours per day for 10 days
Hence, the correct answer is 0.5 hours.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books