Question : The Ghatampur thermal power plant, approved by Cabinet, is to be set up in__________.
Option 1: Rajasthan
Option 2: Uttar Pradesh
Option 3: Karnataka
Option 4: Madhya Pradesh
Correct Answer: Uttar Pradesh
Solution : The correct answer is Uttar Pradesh .
The Ghatampur thermal power station of Neyveli Lignite Corporation (NLC) is a joint venture between NLC and the Uttar Pradesh government. It will be built in Ghatampur district in Kanpur, Uttar Pradesh, and run on coal. The project would provide 1478.28 MW of energy to Uttar Pradesh and 492.72 MW of energy to Assam.