Question : The ratio of time taken to complete a work by a man and a woman is 2 : 3. The man and the woman can complete the work together in 24 days. In how many days can the woman complete the work alone?
Option 1: 20 days
Option 2: 40 days
Option 3: 60 days
Option 4: 30 days
New: SSC CHSL tier 1 answer key 2024 out | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 60 days
Solution : A man and a woman can complete the work together in 24 days. Time = $\frac{\text{Work}}{\text{Efficiency}}$ Time is inversely proportional to efficiency. ⇒ Ratio of time taken = $2 : 3$ $\therefore$ Ratio of efficiencies = $3 : 2$ Total work = $(3 + 2)\times24=120$ $\therefore$ Time take by a woman = $\frac{120}{2}$ = 60 days Hence, the correct answer is 60 days.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : A and B can finish a work together in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days can A alone finish the job?
Question : A and B together can complete a work in 20 days. B and C together can complete the same work in 15 days. If A, B, and C all work together, then the same work gets completed in 10 days. How many days will A and C together take to complete the same work?
Question : Ali, Avtar Singh, and Ashok working together can finish a work in 8 days. Ali alone can do it in 20 days and Avtar Singh alone can do it in 24 days. In how many days can Ashok alone do the same work?
Question : P, Q, and R can complete a work alone in 12,15, and 20 days respectively. They started the work together. P left the work 8 days before the work was completed and Q left the work 5 days after P had left. R completed the remaining work alone. How many days will be required to
Question : S does half as much work as T in $\frac{1}{8}$th of the time taken by T. If they together complete a work in 60 days, then how many days shall S alone take to complete that work?