Question : Three men can complete a piece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will it take to complete the remaining work?
Option 1: 1 day
Option 2: 2 days
Option 3: 3 days
Option 4: 4 days
New: SSC CHSL tier 1 answer key 2024 out | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 2 days
Solution : Given: Three men can complete a piece of work in 6 days. Part of work done in 2 day = $\frac{1}{6}×2=\frac{1}{3}$ Remaining work = $1-\frac{1}{3}=\frac{2}{3}$ We know that: $\frac{M_1 ×D_1}{W_1}=\frac{M_2 ×D_2}{W_2}$ Where $M_1$ and $M_2$ are the numbers of men, and $D_1$ and $D_2$ are days, and $W_1$ and $W_2$ are work done. ⇒ $\frac{3 ×2}{\frac{1}{3}}=\frac{6 ×D_2}{\frac{2}{3}}$ ⇒ $D_2=\frac{12}{3}$ = 2 days Hence, the correct answer is 2 days.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : 40 men can complete a work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will it now take to complete the remaining work?
Question : 16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left and 4 women joined them. How many days will it take them to complete the remaining work?
Question : If 4 men or 6 women can do a piece of work in 12 days, working 7 hours a day. How many days will it take to complete a work twice as large, with 10 men and 3 women working together 8 hours a day?
Question : Rama alone can do a work in 5 days working 4 hours a day. Seema alone can do the same work in 3 days working 10 hours a day. How many hours do they need to work together in a day to complete the same work in 6 days?
Question : 4 men and 8 women complete a job in 10 days and 5 men and 24 women complete the same work in 4 days. In how many days will 1 man and 1 woman complete the same work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile