1 View

Question : Three men can complete a piece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will it take to complete the remaining work?

Option 1: 1 day

Option 2: 2 days

Option 3: 3 days

Option 4: 4 days


Team Careers360 12th Jan, 2024
Answer (1)
Team Careers360 20th Jan, 2024

Correct Answer: 2 days


Solution : Given: Three men can complete a piece of work in 6 days.
Part of work done in 2 day = $\frac{1}{6}×2=\frac{1}{3}$
Remaining work = $1-\frac{1}{3}=\frac{2}{3}$
We know that: $\frac{M_1 ×D_1}{W_1}=\frac{M_2 ×D_2}{W_2}$
Where $M_1$ and $M_2$ are the numbers of men, and $D_1$ and $D_2$ are days, and $W_1$ and $W_2$ are work done.
⇒ $\frac{3 ×2}{\frac{1}{3}}=\frac{6 ×D_2}{\frac{2}{3}}$
⇒ $D_2=\frac{12}{3}$ = 2 days
Hence, the correct answer is 2 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books