Question : Three people A, B, and C worked together and finished a work in 9 days. If A alone can finish the same work in 18 days, and B alone in 30 days, then the number of days C alone will take is:

Option 1: 36 days

Option 2: 45 days

Option 3: 40 days

Option 4: 54 days


Team Careers360 12th Jan, 2024
Answer (1)
Team Careers360 14th Jan, 2024

Correct Answer: 45 days


Solution : Let $x$ be the total work.
A alone can finish the same work in 18 days.
So 1 day's work of A = $\frac{1}{18}$ of the work
B alone can finish the same work in 30 days.
So 1 day's work of B = $\frac{1}{30}$ of the work
Let C take $y$ days to complete the work alone.
When A, B, and C work together, their combined work rate is $\frac{1}{18}+\frac{1}{30}+\frac{1}{y}$ of the work per day.
The combined work rate of A, B, and C is given by $\frac19$ of the work per day.
⇒ $\frac{1}{18}+\frac{1}{30}+\frac{1}{y}=\frac{1}{9}$
⇒ $\frac{1}{y}=\frac{1}{9}-\frac{1}{18}-\frac{1}{30}$
⇒ $\frac{1}{y}=\frac{10-5-3}{90}$
⇒ $\frac{1}{y}=\frac{2}{90}=\frac{1}{45}$
⇒ $y=45$ days
Hence, the correct answer is 45 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books