Question : Three people A, B, and C worked together and finished a work in 9 days. If A alone can finish the same work in 18 days, and B alone in 30 days, then the number of days C alone will take is:

Option 1: 36 days

Option 2: 45 days

Option 3: 40 days

Option 4: 54 days


Team Careers360 12th Jan, 2024
Answer (1)
Team Careers360 14th Jan, 2024

Correct Answer: 45 days


Solution : Let $x$ be the total work.
A alone can finish the same work in 18 days.
So 1 day's work of A = $\frac{1}{18}$ of the work
B alone can finish the same work in 30 days.
So 1 day's work of B = $\frac{1}{30}$ of the work
Let C take $y$ days to complete the work alone.
When A, B, and C work together, their combined work rate is $\frac{1}{18}+\frac{1}{30}+\frac{1}{y}$ of the work per day.
The combined work rate of A, B, and C is given by $\frac19$ of the work per day.
⇒ $\frac{1}{18}+\frac{1}{30}+\frac{1}{y}=\frac{1}{9}$
⇒ $\frac{1}{y}=\frac{1}{9}-\frac{1}{18}-\frac{1}{30}$
⇒ $\frac{1}{y}=\frac{10-5-3}{90}$
⇒ $\frac{1}{y}=\frac{2}{90}=\frac{1}{45}$
⇒ $y=45$ days
Hence, the correct answer is 45 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books