47 Views

Question : To do a certain task X would take 3 times as long as Y and Z together, and Z would take 4 times as long as Y and X together. Three of them together can complete the task in 10 days. How much time is taken by X and Z to complete the task?

Option 1: $18 \frac{2}{9}$ days

Option 2: $20 \frac{1}{9}$ days

Option 3: $21 \frac{1}{9}$ days

Option 4: $22 \frac{2}{9}$ days


Team Careers360 15th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: $22 \frac{2}{9}$ days


Solution : Given,
To do a certain task,
X takes 3 times as long as Y and Z together,
Z takes 4 times as long as Y and X together,
Three of them together can complete the task in 10 days.
We know, Total work = Time × Efficiency
Let the efficiency of X, Y, and Z be a, b, and c respectively and total work be W
According to the question,
W = 10(a + b + c) ....................(1)
X takes 3 times (Y + Z)
⇒ (b + c) = 3a
Putting this in (1)
⇒ W = 10(a + 3a) ⇒ W = 10(4a) ⇒ W = 40a ⇒ a = $\frac{\text{W}}{40}$
Z takes 4 times (X + Y)
⇒ (a + b) = 4c
Putting this in (1)
⇒ W = 10(4c + c) ⇒ W = 10(5c) ⇒ W = 50c ⇒ c = $\frac{\text{W}}{50}$
Now X and Z are working together and considering total work as 1 then,
⇒ X + Z = a + c
⇒ X + Z = $\frac{1}{40} + \frac{1}{50}$
⇒ X + Z = $\frac{5 + 4}{200}$
⇒ X + Z = $\frac{9}{200}$
⇒ Time taken by X and Z to complete a task = $\frac{200}{9}$ days = $22\frac29$ days
Hence, the correct answer is $22\frac29$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books