Question : To do a certain work, the ratio of the efficiencies of A and B is 7 : 5. Working together, they can complete the same work in $17 \frac{1}{2}$ days. A alone will complete 60% of the same work in:
Option 1: 18 days
Option 2: 15 days
Option 3: 16 days
Option 4: 21 days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 18 days
Solution : Let the efficiency of A be $E_A$ and the efficiency of B as $E_B$. Given that the ratio of the efficiencies of A and B is 7 : 5, for some constant $x$. $E_A = 7x$ $E_B = 5x$ The total amount of work done by A and B together in one day. $E_A + E_B = 7x + 5x = 12x$ Given that A and B together can complete the work in $17\frac{1}{2}$ days. The total work $W$, $W = (E_A + E_B) \times \text{time} = 12x \times 17\frac{1}{2} = 210x$ The time it will take for A to complete 60% of the work alone. The amount of work A needs to do = $0.6W = 0.6 \times 210x = 126x$ The time it takes for A to complete this amount of work $=\frac{126x}{7x} = 18$ days Hence, the correct answer is 18 days.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : Raju and Rajat working together take 5 days to complete a piece of work. If Raju alone can do it in 7 days, how long would Rajat take to complete the same work?
Question : A, B, and C working alone, can complete a job in 16, 24, and 36 days, respectively. In how many days can they complete the job if they work together?
Question : A alone can do a work in 14 days. B alone can do the same work in 28 days. C alone can do the same work in 56 days. They started the work together and completed the work such that B was not working in the last 2 days and A did not work in the last 3 days. In how many days
Question : P and Q together complete a job in $4 \frac{2}{5}$ days. R and S complete the same job in $4 \frac{8}{9}$ days. If P, Q, R, and S work together, how many days do they need to complete the same job?
Question : A can do $\frac{1}{3}$rd of a piece of work in 32 days, B can do $37 \frac{1}{2}$% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left and A joined C and together, completed the
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile