Question : Tom can do a piece of work in 7 days, whereas Jay can do the same work in 14 days. How long will it take to finish the work if both work together?

Option 1: $5 \frac{2}{3}$ days

Option 2: $4 \frac{2}{3}$ days

Option 3: $7 \frac{2}{3}$ days

Option 4: $2 \frac{2}{3}$ days


Team Careers360 7th Jan, 2024
Answer (1)
Team Careers360 15th Jan, 2024

Correct Answer: $4 \frac{2}{3}$ days


Solution : Time taken by Tom to complete the work = 7 days
Part of work done by Tom in a day = $\frac{1}{7}$
Time taken by Jay to complete the work = 14 days
Part of work done by Jay in a day = $\frac{1}{14}$
Part of the work done by Tom and Jay together in a day = $\frac{1}{7}+\frac{1}{14}=\frac{2+1}{14} = \frac{3}{14}$
Time taken by Tom and Jay together to complete the work = $\frac{14}{3} = 4\frac{2}{3}$ days
Hence, the correct answer is $4\frac{2}{3}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books