Question : Vijay is 10% more efficient than Vikas. If Vikas can complete a piece of work in 33 days, Vijay can complete the same work in how many days?

Option 1: 25

Option 2: 27

Option 3: 30

Option 4: 36


Team Careers360 20th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 30


Solution : Let Vikas be 100% efficient.
Then Vijay will be 110% efficient.
Now, 100% efficient can do work in 33 days,
1% efficient will do work in $33 \times 100$ days.
$\therefore$ 110% efficient can do work in $\frac{33 \times 100}{110}$ = 30 days
Hence, the correct answer is 30.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books