Question : Vijay is 10% more efficient than Vikas. If Vikas can complete a piece of work in 33 days, Vijay can complete the same work in how many days?

Option 1: 25

Option 2: 27

Option 3: 30

Option 4: 36


Team Careers360 20th Jan, 2024
Answer (1)
Team Careers360 22nd Jan, 2024

Correct Answer: 30


Solution : Let Vikas be 100% efficient.
Then Vijay will be 110% efficient.
Now, 100% efficient can do work in 33 days,
1% efficient will do work in $33 \times 100$ days.
$\therefore$ 110% efficient can do work in $\frac{33 \times 100}{110}$ = 30 days
Hence, the correct answer is 30.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books