51 Views

Question : Virat can complete a task in 30 days and Daniel is 60% more efficient than Virat in completing the same task. Find the time total taken by Daniel to complete the task.

Option 1: $16 \frac{3}{5}$ days

Option 2: $18 \frac{3}{4}$ days

Option 3: $19 \frac{5}{3}$ days

Option 4: $17 \frac{5}{3}$ days


Team Careers360 17th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: $18 \frac{3}{4}$ days


Solution : Given: Virat can do a task in 30 days.
Daniel's efficiency = 160% of Virat
Work = Efficiency × Time
Let Virat's efficiency be 100 units.
Daniel's efficiency = 160 units
Total work = 100 × 30 = 3000 units
Total work done by Daniel = $\frac{3000}{160}$ = $\frac{75}{4}$ = 18$\frac{3}{4}$
Hence, the correct answer is 18$\frac{3}{4}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books