Question : Virat can complete a task in 30 days and Daniel is 60% more efficient than Virat in completing the same task. Find the time total taken by Daniel to complete the task.
Option 1: $16 \frac{3}{5}$ days
Option 2: $18 \frac{3}{4}$ days
Option 3: $19 \frac{5}{3}$ days
Option 4: $17 \frac{5}{3}$ days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $18 \frac{3}{4}$ days
Solution : Given: Virat can do a task in 30 days. Daniel's efficiency = 160% of Virat Work = Efficiency × Time Let Virat's efficiency be 100 units. Daniel's efficiency = 160 units Total work = 100 × 30 = 3000 units Total work done by Daniel = $\frac{3000}{160}$ = $\frac{75}{4}$ = 18$\frac{3}{4}$ Hence, the correct answer is 18$\frac{3}{4}$ days.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : 8 men can complete a task in 45 days. 8 women can complete the same task in 18 days. In how many days will 5 men and 8 women, together, complete the same task?
Question : A worker completes $\frac{3}{5}$th of a task in 12 days. In how many days will he complete $\frac{3}{4}$th of the task?
Question : A, B, and C working alone, can complete a job in 16, 24, and 36 days, respectively. In how many days can they complete the job if they work together?
Question : A can complete a task in 25 days while B can complete the same task in 30 days. They work on alternate days, starting with A. Both A and B follow this pattern for 5 days and then, A leaves. In how many days will B finish the remaining work?
Question : Rekha alone can complete a task in 16 days and Bina alone can complete the same task in 12 days. Starting with Rekha, they work on alternate days. The task will be completed in: