41 Views

Question : When A alone does a piece of work, he takes 25 days more than the time taken by A and B to do the work together. On the other hand, B alone takes 16 days more than the time taken by A and B to do the work together. How many days will A and B, working together, take to do the work?

Option 1: 24

Option 2: 20

Option 3: 23

Option 4: 22


Team Careers360 19th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 20


Solution : Let the total days to complete the work be $x$.
One day work of A working alone = $\frac{1}{x+25}$
One day work of B working alone = $\frac{1}{x+16}$
According to the question,
$\frac{1}{x+25}+\frac{1}{x+16}=\frac{1}{x}$
⇒ $\frac{x+16+x+25}{(x+25)(x+16)}=\frac{1}{x}$
⇒ $\frac{2x+41}{(x^2+16x+25x+400)}=\frac{1}{x}$
⇒ $\frac{2x+41}{(x^2+41x+400)}=\frac{1}{x}$
⇒ $2x^2+41x=x^2+41x+400$
⇒ $x^2=400$
$\therefore x=20$
Hence, the correct answer is 20.

Know More About

Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Upcoming Exams

Exam Date: 3 Jan, 2026 - 20 Jan, 2026
Application Date: 10 Jan, 2026 - 9 Feb, 2026
Application Date: 11 Dec, 2025 - 11 Jan, 2026
Application Date: 16 Dec, 2025 - 16 Jan, 2026
Tier II Exam Date: 18 Jan, 2026 - 19 Jan, 2026

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books