7 Views

Question : When A alone does a piece of work, he takes 25 days more than the time taken by A and B to do the work together. On the other hand, B alone takes 16 days more than the time taken by A and B to do the work together. How many days will A and B, working together, take to do the work?

Option 1: 24

Option 2: 20

Option 3: 23

Option 4: 22


Team Careers360 19th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 20


Solution : Let the total days to complete the work be $x$.
One day work of A working alone = $\frac{1}{x+25}$
One day work of B working alone = $\frac{1}{x+16}$
According to the question,
$\frac{1}{x+25}+\frac{1}{x+16}=\frac{1}{x}$
⇒ $\frac{x+16+x+25}{(x+25)(x+16)}=\frac{1}{x}$
⇒ $\frac{2x+41}{(x^2+16x+25x+400)}=\frac{1}{x}$
⇒ $\frac{2x+41}{(x^2+41x+400)}=\frac{1}{x}$
⇒ $2x^2+41x=x^2+41x+400$
⇒ $x^2=400$
$\therefore x=20$
Hence, the correct answer is 20.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books