Question : Which of the following is correctly matched concerning the thermal power project?
Option 1: Talcher - Andhra Pradesh
Option 2: Korba - Uttar Pradesh
Option 3: Kawas - Gujarat
Option 4: Ramagundam - Madhya Pradesh
New: SSC MTS Tier 1 Answer key 2024 out
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: Kawas - Gujarat
Solution : The correct answer is Kawas - Gujarat.
Answer Key | Cutoff | Selection Process | Preparation Tips | Eligibility | Application | Exam Pattern
Question : Through which states does the river Chambal flow?
Question : Kawas Thermal Power Station is located in which of the following states?
Question : Which Indian state government launched a cleanliness drive called Project CLAP?
Question : The famous Hirakud Captive Thermal Power plant is located in which of the following states?
Question : The famous Dhamek Stupa is located in which of the following states?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile