Question : Which state/UT constructed 3,300 km of rural roads in 2020-21 under the Pradhan Mantri Gram Sadak Yojana?
Option 1: Uttarakhand
Option 2: Himachal Pradesh
Option 3: Delhi
Option 4: Jammu and Kashmir
Correct Answer: Jammu and Kashmir
Solution : The correct option is Jammu and Kashmir .
In the fiscal year 2020–21, the region of Jammu and Kashmir demonstrated significant progress in rural infrastructure development by successfully constructing 3,300 km of rural roads under the Pradhan Mantri Gramme Sadak Yojana (PMGSY). This milestone reflects a substantial commitment to enhancing connectivity and accessibility in rural areas, contributing to the overarching goals of the PMGSY Scheme.