Question : Working 12 hours per day, Raj can complete a work in 12 days. How many hours per day he should work to finish the same work in 9 days?

Option 1: 20 hours

Option 2: 24 hours

Option 3: 12 hours

Option 4: 16 hours


Team Careers360 13th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 16 hours


Solution : We know, H 1 × D 1 = H 2 × D 2 , Where H 1 , H 2 are hours per day and D 1 , D 2 are number of days.
Let the required hours be $x$.
So, 12 × 12 = $x$ × 9
⇒ $x$ = 16
Hence, the correct answer is 16 hours.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books