Question : Working 12 hours per day, Raj can complete a work in 12 days. How many hours per day he should work to finish the same work in 9 days?

Option 1: 20 hours

Option 2: 24 hours

Option 3: 12 hours

Option 4: 16 hours


Team Careers360 13th Jan, 2024
Answer (1)
Team Careers360 23rd Jan, 2024

Correct Answer: 16 hours


Solution : We know, H 1 × D 1 = H 2 × D 2 , Where H 1 , H 2 are hours per day and D 1 , D 2 are number of days.
Let the required hours be $x$.
So, 12 × 12 = $x$ × 9
⇒ $x$ = 16
Hence, the correct answer is 16 hours.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books