Question : Working 15 hours a day, Vaibhav can complete a piece of work in 35 days. How many hours a day should he work to finish the work in 25 days?
Option 1: 21 hours
Option 2: 20 hours
Option 3: 18 hours
Option 4: 17 hours
Correct Answer: 21 hours
Solution :
Total time taken = 15 × 35 = 525 hours
$\therefore$ Time needed daily to complete the work in 25 days = $\frac{525}{25}$ = 21
Hence, the correct answer is 21 hours.
Related Questions
Know More about
Staff Selection Commission Multi Tasking ...
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Get Updates BrochureYour Staff Selection Commission Multi Tasking Staff Exam brochure has been successfully mailed to your registered email id “”.