Question : Working 5 hours a day, A can complete a task in 8 days, and working 6 hours a day, B can finish the same task in 10 days. Working 8 hours daily, they can jointly complete the task in _____.
Option 1: 5 days
Option 2: 3 days
Option 3: 4.5 days
Option 4: 6 days
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 3 days
Solution : If a person works in $n$ days working $y$ hours a day, then One hour's work of that person is $\frac{1}{ny}$ part of the total work. One hour's work of A $= \frac{1}{(8 × 5)}= \frac{1}{40}$ One hour's work of B $= \frac{1}{(10\times 6)} = \frac{1}{60}$ One hour's work of both A and B = one day's work of A + one day's work of B = $\frac{1}{40} +\frac{1}{60}$ = $\frac{3+2}{120}$ = $\frac{5}{120}=\frac{1}{24}$ Then the whole work will be done by A and B together in 24 hours. Working 8 hours a day both A and B can complete the work in = $\frac{24}{8}$ = 3 days Hence, the correct answer is 3 days.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : A can do a piece of work in 6 days, working 8 hours a day, while B can do the same work in 4 days, working 10 hours a day. If the work has to be completed in 5 days, how many hours do they need to work together in a day?
Question : 4 women or 6 boys can finish a work in the same number of days. A boy can finish it in 60 days. In how many days can 5 women finish the work, working together every day?
Question : A's efficiency is twice that of B's. A can work only for 8 hours a day while B can work for 12 hours a day. If A can finish a task in 12 days, in how many days can B finish the same task?
Question : Working for 10 hours per day, 6 men can build a wall in a certain number of days. By working for how many hours/per day can 12 men build the wall on the same day?
Question : 15 men take 20 days to complete a job, working 8 hours a day. The number of hours a day that 20 men should take to complete the job in 12 days.
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile