Question : Working 7 hours a day, 18 persons can complete a certain work in 32 days. In how many days would 14 persons complete the same work, working 8 hours a day?
Option 1: 42
Option 2: 30
Option 3: 35
Option 4: 36
Correct Answer: 36
Solution : Given: Working 7 hours a day, 18 persons can complete a certain work in 32 days. Usse the formula, $M_1\times D_1 \times T_1=M_2\times D_2 \times T_2$, where $M_1$, $M_2$, $D_1$, $D_2$, $T_1$ and $T_2$ are the men, days and time respectively. ⇒ $18\times 32 \times 7=14\times D_2 \times 8$ ⇒ $D_2=36$ days Hence, the correct answer is 36.
Result | Eligibility | Application | Selection Process | Cutoff | Admit Card | Preparation Tips
Question : If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day?
Question : If 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 men do the same work by working 6 hours a day?
Question : A can complete a certain work in 35 days and B can complete the same work in 15 days. They worked together for 7 days, and then B left the work. In how many days will A alone complete 60% of the remaining work?
Question : A and B together can do a certain work in $x$ days. Working alone, A and B can do the same work in ($x$ + 8) and ($x$ + 18) days, respectively. A and B together will complete $\frac{5}{6}$th of the same work in:
Question : If 12 carpenters working 6 hours a day can make 460 chairs in 240 days, then the number of chairs made by 18 carpenters in 36 days each working 8 hours a day is: