Question : Working for 10 hours per day, 6 men can build a wall in a certain number of days. By working for how many hours/per day can 12 men build the wall on the same day?
Option 1: 7 hours 30 minutes
Option 2: 5 hours
Option 3: 20 hours
Option 4: 10 hours
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 5 hours
Solution : Total time needed to complete the work = 6 × 10 = 60 hours Time needed by 12 men to complete the work = $\frac{60}{12}$ = 5 hours Hence, the correct answer is 5 hours.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : 15 men take 20 days to complete a job, working 8 hours a day. The number of hours a day that 20 men should take to complete the job in 12 days.
Question : Working 5 hours a day, A can complete a task in 8 days, and working 6 hours a day, B can finish the same task in 10 days. Working 8 hours daily, they can jointly complete the task in _____.
Question : If 90 men can do a certain job in 16 days, working 12 hours per day, then the part of that work which can be completed by 70 men in 24 days, working 8 hours per day is:
Question : A can do a piece of work in 6 days, working 8 hours a day, while B can do the same work in 4 days, working 10 hours a day. If the work has to be completed in 5 days, how many hours do they need to work together in a day?
Question : Two men and 7 women can complete a work in 28 days, whereas 6 men and 16 women can do the same work in 11 days. In how many days will 5 men and 4 women, working together, complete the same work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile