1 View

Question : X alone can complete a piece of work in 16 days, while Y alone can complete the same work in 24 days. They work on alternate days starting with Y. In how many days will 50% of the total work be completed?

Option 1: $\frac{24}{3}$ days

Option 2: $\frac{29}{3}$ days

Option 3: $\frac{32}{3}$ days

Option 4: 9 days


Team Careers360 18th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: $\frac{29}{3}$ days


Solution : Time taken by X to complete the work = 16 days
Part of work done by X in a day = $\frac{1}{16}$
Time taken by X to complete the work = 24 days
Part of work done by X in a day = $\frac{1}{24}$
Part of work done by X and Y in 2 days = $\frac{1}{24}+\frac{1}{16}=\frac{2+3}{48}=\frac{5}{48}$
Part of work done by X and Y in 8 days = $\frac{5×4}{48} = \frac{20}{48}$
Part of work done by Y in 9th day = $\frac{1}{24} = \frac{2}{24}$
Remaining work = $\frac{24-20-2}{48} = \frac{2}{48}$
Time taken by X to do the remaining work = $\frac{ \frac{2}{48}}{\frac{1}{16}} = \frac{2}{3}$ day
Total time taken = $9 + \frac{2}{3} = \frac{29}{3}$ days
Hence, the correct answer is $\frac{29}{3}$ days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books