Question : X alone can complete a piece of work in 16 days, while Y alone can complete the same work in 24 days. They work on alternate days starting with Y. In how many days will 50% of the total work be completed?
Option 1: $\frac{24}{3}$ days
Option 2: $\frac{29}{3}$ days
Option 3: $\frac{32}{3}$ days
Option 4: 9 days
New: SSC MTS 2024 Application Form OUT; Direct Link
Don't Miss: Month-wise Current Affairs | Upcoming Government Exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $\frac{29}{3}$ days
Solution : Time taken by X to complete the work = 16 days Part of work done by X in a day = $\frac{1}{16}$ Time taken by X to complete the work = 24 days Part of work done by X in a day = $\frac{1}{24}$ Part of work done by X and Y in 2 days = $\frac{1}{24}+\frac{1}{16}=\frac{2+3}{48}=\frac{5}{48}$ Part of work done by X and Y in 8 days = $\frac{5×4}{48} = \frac{20}{48}$ Part of work done by Y in 9th day = $\frac{1}{24} = \frac{2}{24}$ Remaining work = $\frac{24-20-2}{48} = \frac{2}{48}$ Time taken by X to do the remaining work = $\frac{ \frac{2}{48}}{\frac{1}{16}} = \frac{2}{3}$ day Total time taken = $9 + \frac{2}{3} = \frac{29}{3}$ days Hence, the correct answer is $\frac{29}{3}$ days.
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Question : Akbar can complete a piece of work alone in 12 days, while Anthony can complete the same work alone in 20 days. If they work on alternate days with Anthony starting the work, then in how many days can they complete the whole work?
Question : A alone can do a piece of work in 10 days. B alone can do the same work in 12 days. They work on alternate days starting with A. In how many days will they complete $\frac{3}{4}$th of the total work?
Question : A piece of work can be completed by P and Q together in 24 days, and the same piece of work can be completed by R alone in 60 days. If P and R together can do the same work in 36 days, then find the time taken by Q to complete this piece of work alone.
Question : X and Y together can do a piece of work in 45 days. If Y alone can complete it in 180 days, then in how many days X alone can complete the work?
Question : Riya alone can complete a piece of work in 6 days while Siya alone can do the same work in 9 days. If they both work together, then how many days will be required to finish the work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile