Question : X alone can finish a work in 18 days, and Y alone can finish the same work in 9 days. If X, Y, and Z together can finish the same work in 4 days, then in how many days Z alone can finish the work?

Option 1: 12 days

Option 2: 10 days

Option 3: 14 days

Option 4: 16 days


Team Careers360 14th Jan, 2024
Answer (1)
Team Careers360 20th Jan, 2024

Correct Answer: 12 days


Solution : Let the rate at which X, Y, and Z can finish the work as $R_x, R_y$ and $R_z$, respectively.
Given that X can finish the work in 18 days.
⇒ $R_x=\frac{1}{18}$ work per day
Given that Y can finish the work in 9 days.
⇒ $R_y=\frac{1}{9}$ work per day
Given that X, Y, and Z together can finish the work in 4 days.
⇒ $R_x + R_y + R_z=\frac{1}{4}$ work per day
⇒ $R_z=(R_x + R_y + R_z) -R_x - R_y=\frac{1}{4}-\frac{1}{18}-\frac{1}{9}=\frac{1}{12}$ work per day
So, Z alone can finish the work in 12 days.
Hence, the correct answer is 12 days.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books