Question : X and Y can complete a piece of work in 12 and 60 days respectively. They are contracted to complete the work together for Rs. 24,000. What will be the share of X?

Option 1: Rs. 18,000

Option 2: Rs. 16,000

Option 3: Rs. 20,000

Option 4: Rs. 21,000


Team Careers360 7th Jan, 2024
Answer (1)
Team Careers360 10th Jan, 2024

Correct Answer: Rs. 20,000


Solution : Given: X and Y can complete a piece of work in 12 and 60 days.
The total work of X and Y is LCM of (12, 60) = 60 units
1 day's work by X $=\frac{60}{12}=5$
1 day's work by Y $=\frac{60}{60}=1$
So, the ratio of their efficiency $= 5 : 1$
Share of X $=\frac{5}{6}\times 24000=$ Rs. $20000$
Hence, the correct answer is Rs. 20,000.

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books