Question : X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in:
Option 1: 18 days
Option 2: 27 days
Option 3: 36 days
Option 4: 42 days
New: SSC CHSL tier 1 answer key 2024 out | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
Correct Answer: 36 days
Solution :
Time taken by X to complete the work = 24 days
Work done by X in 1 day = $\frac{1}{24}$th of the total work.
Work done by X in 4 days = $4×\frac{1}{24}=\frac{1}{6}$
The remaining work = $1-\frac{1}{6}=\frac{5}{6}$
X and Y together completed the remaining work in (16 – 4) days = 12 days
Therefore, Work done by X and Y together in a day = $\frac{\frac{5}{6}}{12}=\frac{5}{72}$ of the work
Now, Work done by X in a day + Work done by Y in a day = $\frac{5}{72}$ of the work
So, Y alone can do $=\frac{5}{72} - \frac{1}{24}=\frac{2}{72}=\frac{1}{36}$ of the work in one day
$\therefore$ Y alone can do the work in = 36 days
Hence, the correct answer is 36 days.
Related Questions
Know More about
Staff Selection Commission Combined High ...
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Get Updates BrochureYour Staff Selection Commission Combined Higher Secondary Level Exam brochure has been successfully mailed to your registered email id “”.