Question : X can do a piece of work in 24 days. When he had worked for 4 days, Y joined him. If complete work was finished in 16 days, Y can alone finish that work in:
Option 1: 18 days
Option 2: 27 days
Option 3: 36 days
Option 4: 42 days
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 36 days
Solution : Time taken by X to complete the work = 24 days Work done by X in 1 day = $\frac{1}{24}$th of the total work. Work done by X in 4 days = $4×\frac{1}{24}=\frac{1}{6}$ The remaining work = $1-\frac{1}{6}=\frac{5}{6}$ X and Y together completed the remaining work in (16 – 4) days = 12 days Therefore, Work done by X and Y together in a day = $\frac{\frac{5}{6}}{12}=\frac{5}{72}$ of the work Now, Work done by X in a day + Work done by Y in a day = $\frac{5}{72}$ of the work So, Y alone can do $=\frac{5}{72} - \frac{1}{24}=\frac{2}{72}=\frac{1}{36}$ of the work in one day $\therefore$ Y alone can do the work in = 36 days Hence, the correct answer is 36 days.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : Ram can complete a piece of work in 18 days, Reena can complete the same work in 12 days, and with the help of Shyam, they finish the same work in 6 days. In how many days can Shyam alone complete the same work?
Question : Three people A, B, and C worked together and finished a work in 9 days. If A alone can finish the same work in 18 days, and B alone in 30 days, then the number of days C alone will take is:
Question : A can finish a work in 15 days, B can finish the same work in 25 days. They work together for 5 days. The rest of the work is finished by A and C in 4 days. Then C alone can finish the work in:
Question : A alone can make a table in 30 days while B alone can make it in 15 days. B started work alone and worked for 8 days. In how many days A alone can finish the remaining work?
Question : A can finish a work in 24 days and B in 30 days, individually. They work together for 11 days. The percentage of the work still to be finished will be:
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile