47 Views

Question : X, Y, and Z can complete a piece of work in 20, 12, and 28 days respectively. If all work together, the approximate number of days to complete the work will be:

Option 1: 6

Option 2: 7

Option 3: 4

Option 4: 5


Team Careers360 3rd Jan, 2024
Answer (1)
Team Careers360 18th Jan, 2024

Correct Answer: 6


Solution : The time taken by X, Y, and Z to complete the work is 20, 12, and 28 days respectively.
Work done by X, Y, and Z in a day is $\frac{1}{20}$, $\frac{1}{12}$, and $\frac{1}{28}$ respectively.
Work done by X, Y, and Z together in a day = $\frac{1}{20}+\frac{1}{12}+\frac{1}{28}$ = $\frac{71}{420}$
So, time is taken by X, Y, and Z to complete the work together = $ \frac{420}{71}\approx$ 6 days
Hence, the correct answer is 6.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books