Question : 18 men can do a piece of work in 20 days. After working for 8 days, they get a notice to complete the work 4 days earlier than originally scheduled. How many more men will be required to be hired to complete the work as per the new schedule?
Option 1: 9
Option 2: 12
Option 3: 8
Option 4: 15
Correct Answer: 9
Solution :
18 men can do a piece of work in = 20 days
After working for 8 days, they get a notice to complete the work 4 days earlier than originally scheduled
The total work = 18 × 20 = 360 units
Work for 8 days then the work completed in 8 days = 18 Men × 8 Days = 144 units
The work done in 8 days by 18 men = 144 units
The remaining work = 360 – 144 = 216
The remaining days is = 20– 4 – 8 = 20 – 12 = 8 days
The more men required to complete the work in 8 days are $x$.
⇒ 216 = (18 + $x$) × 8
⇒ 18 + $x$ = 27
⇒ $x$ = 27 – 18 = 9
$\therefore$ 9 more men are required to complete the work as per the new schedule.
Hence, the correct answer is 9.
Related Questions
Know More about
Staff Selection Commission Multi Tasking ...
Application | Cutoff | Selection Process | Preparation Tips | Eligibility | Exam Pattern | Admit Card
Get Updates BrochureYour Staff Selection Commission Multi Tasking Staff Exam brochure has been successfully mailed to your registered email id “”.