Question : 30 men can complete a work in 12 days. After 6 days, 24 more men joined them. How many days will it now take to complete the remaining work?
Option 1: $3\frac{1}{3}$ days
Option 2: $3\frac{2}{3}$ days
Option 3: $3\frac{1}{2}$ days
Option 4: $2\frac{1}{3}$ days
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: $3\frac{1}{3}$ days
Solution : Given: 30 men can complete a work in 12 days. After 6 days, 24 more men joined them. Let total work = (30 × 12) = 360 units. So, work done by 30 men in 1 day = $\frac{360}{12}=30$ units, And work done by 30 men in 6 days = (30 × 6) = 180 units. Remaining work = (360 – 180) = 180 units. After 6 days 24 men joined, So, total men = (30 + 24) = 54 Therefore, time required to complete the remaining work = $\frac{180}{54}=3\frac{1}{3}$ days. Hence, the correct answer is $3\frac{1}{3}$ days.
Candidates can download this ebook to know all about SSC CGL.
Result | Eligibility | Application | Selection Process | Preparation Tips | Admit Card | Answer Key
Question : 10 women took 16 days to complete a work which can be completed by 6 men in 8 days. 12 men started working and after 2 days 6 men left and 5 women joined them. In how many days will the remaining work be completed?
Question : 12 men can complete a work in 10 days. How many more men are required to complete the work in 6 days?
Question : 10 men can do work in 25 days. After 12 days of work, 3 more men were engaged to finish the work. The number of days required to complete the remaining work is:
Question : 12 men and 12 women can complete a piece of work in 9 days. 6 men and 15 women can complete the same work in 12 days. How long (in days) would it take 9 women to complete half the work?
Question : 15 men complete a work in 10 days. 15 women complete the same work in 12 days. If all these men and women work together, then the number of days required to complete that work is: