Question : 30 men can complete a work in 12 days. After 6 days, 24 more men joined them. How many days will it now take to complete the remaining work?

Option 1: $3\frac{1}{3}$ days

Option 2: $3\frac{2}{3}$ days

Option 3: $3\frac{1}{2}$ days

Option 4: $2\frac{1}{3}$ days


Team Careers360 17th Jan, 2024
Answer (1)
Team Careers360 21st Jan, 2024

Correct Answer: $3\frac{1}{3}$ days


Solution : Given: 30 men can complete a work in 12 days. After 6 days, 24 more men joined them.
Let total work = (30 × 12) = 360 units.
So, work done by 30 men in 1 day = $\frac{360}{12}=30$ units,
And work done by 30 men in 6 days = (30 × 6) = 180 units.
Remaining work = (360 – 180) = 180 units.
After 6 days 24 men joined,
So, total men = (30 + 24) = 54
Therefore, time required to complete the remaining work = $\frac{180}{54}=3\frac{1}{3}$ days.
Hence, the correct answer is $3\frac{1}{3}$ days.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books