Question : A alone can do $\frac{2}{5}$ of a work in 12 days. B is 25% more efficient than A. C alone can do the same work in 12 days less than B. D is 25% less efficient than C. If they all work together, then the work will be completed in how many days?
Option 1: $\frac{240}{53}$ days
Option 2: $\frac{180}{43}$ days
Option 3: $\frac{200}{51}$ days
Option 4: $\frac{300}{47}$ days
Latest: SSC CGL Tier 1 Result 2024 Out | SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL Tier 1 Scorecard 2024 Released | SSC CGL complete guide
Suggested: Month-wise Current Affairs | Upcoming Government Exams
Correct Answer: $\frac{240}{53}$ days
Solution : Given: A alone can do $\frac{2}{5}$ of a work in 12 days. Total work = Efficiency × Number of days A will finish one work in $12 \times \frac{5}{2}=30$ days. A's work in a day is $\frac{1}{30}$ of the total work. Since B is 25% more productive than A. B will finish the work in $\frac{100}{125}\times 30 =\frac{4}{5}\times 30=24$ days. One day's work for B equals $\frac{1}{24}$ of the total work. C requires 12 fewer days than B = 24 – 12 = 12 days. C's one day work $\frac{1}{12}$ of the total work. Currently, D is 25% less productive than C. So, D will finish the task in $\frac{100}{75}\times 12 = 16$ days. D's one day work $\frac{1}{16}$ of the total work. Together one day work $=\frac{1}{30}+\frac{1}{24}+\frac{1}{12}+\frac{1}{16}$. $=\frac{8+10+20+15}{240}=\frac{53}{240}$ part of work. The time taken by all together to complete the work = $\frac{240}{53}$ days. Hence, the correct answer is $\frac{240}{53}$ days.
Candidates can download this ebook to know all about SSC CGL.
Result | Eligibility | Application | Selection Process | Preparation Tips | Admit Card | Answer Key
Question : A, B and C together can complete a work in 12 days. A and B alone can do the same work in 36 days. In how many days can C alone complete the same work?
Question : A can do $\frac{1}{3}$rd of a piece of work in 32 days, B can do $37 \frac{1}{2}$% of the same work in 24 days, while C can do 60% of the same work in 48 days. B and C together started and worked for x days. After x days, B left and A joined C and together, completed the
Question : A is 40% more efficient than B. How much time will they take to work together to complete a job which A alone could have done in 31 days?
Question : A alone can do a work in 14 days. B alone can do the same work in 28 days. C alone can do the same work in 56 days. They started the work together and completed the work such that B was not working in the last 2 days and A did not work in the last 3 days. In how many days
Question : A and B can complete a work together in 48 days. A is 4 times as work-efficient as B. In how many days can B alone complete the work?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile