Question : A alone can make a table in 30 days while B alone can make it in 15 days. B started work alone and worked for 8 days. In how many days A alone can finish the remaining work?

Option 1: 14 days

Option 2: 10 days

Option 3: 12 days

Option 4: 15 days


Team Careers360 12th Jan, 2024
Answer (1)
Team Careers360 24th Jan, 2024

Correct Answer: 14 days


Solution : Given,
A can make a table in 30 days.
B can make a table in 15 days.
B worked for 8 days.
Work done = Time × Work rate
⇒ Rate of A = $\frac{1}{30}$ table/day
⇒ Rate of B = $\frac{1}{15}$ table/day
⇒ Work done by B = Rate × Time = $\frac{1}{15} ×8 = \frac{8}{15}$ table
Remaining work = $1 - \frac{8}{15}=\frac{7}{15}$ table
So, the time taken by A to finish the remaining work $=\frac{\text{Work}}{\text{Rate}}=\frac{\frac{7}{15}}{\frac{1}{30}} = 14$ days
Hence, the correct answer is 14 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books