Question : A alone can make a table in 30 days while B alone can make it in 15 days. B started work alone and worked for 8 days. In how many days A alone can finish the remaining work?
Option 1: 14 days
Option 2: 10 days
Option 3: 12 days
Option 4: 15 days
New: SSC CHSL Tier 2 answer key released | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 14 days
Solution : Given, A can make a table in 30 days. B can make a table in 15 days. B worked for 8 days. Work done = Time × Work rate ⇒ Rate of A = $\frac{1}{30}$ table/day ⇒ Rate of B = $\frac{1}{15}$ table/day ⇒ Work done by B = Rate × Time = $\frac{1}{15} ×8 = \frac{8}{15}$ table Remaining work = $1 - \frac{8}{15}=\frac{7}{15}$ table So, the time taken by A to finish the remaining work $=\frac{\text{Work}}{\text{Rate}}=\frac{\frac{7}{15}}{\frac{1}{30}} = 14$ days Hence, the correct answer is 14 days.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : A can finish a work in 25 days, and B can do the same work in 15 days. B worked for 10 days and left the job. A alone can finish the remaining work in how many days?
Question : A and B can finish a work together in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished the remaining work. In how many days can A alone finish the job?
Question : Ali, Avtar Singh, and Ashok working together can finish a work in 8 days. Ali alone can do it in 20 days and Avtar Singh alone can do it in 24 days. In how many days can Ashok alone do the same work?
Question : Three people A, B, and C worked together and finished a work in 9 days. If A alone can finish the same work in 18 days, and B alone in 30 days, then the number of days C alone will take is:
Question : A can finish a work in 15 days, B can finish the same work in 25 days. They work together for 5 days. The rest of the work is finished by A and C in 4 days. Then C alone can finish the work in: