22 Views

Question : A and B can do a piece of work in 10 days and 15 days, respectively. They worked together, but 5 days before the completion of the work, A left. In how many days was the work completed?

Option 1: 4

Option 2: 8

Option 3: 6

Option 4: 9


Team Careers360 23rd Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 9


Solution : Given: Time taken by A = 10 days
Time taken by B = 15 days
A left the work 5 days before the completion of the work.
Let the total work be 1 unit.
⇒ A's 1 day work = $\frac{1}{10}$
And B's 1 day work = $\frac{1}{15}$
Both (A + B)'s 1 day's work = $\frac{1}{10}+\frac{1}{15}$ = $\frac{3+2}{30}=\frac{5}{30}=\frac{1}{6}$
Let $t$ be the number of days A and B worked together before A left.
Now, A left 5 days before the completion of the work
⇒ For $(t-5)$ days, A and B worked together.
Work done in $(t-5)$ days = $\frac{1}{6}\times (t-5)$
Work done by B in 5 days = $5\times\frac{1}{15}$ = $\frac{1}{3}$
Now, Work done together in $(t-5)$ days + work done by B alone in 5 days = 1
⇒ $\frac{1}{6}\times (t-5)+\frac{1}{3}=1$
⇒ $\frac{t-5+2}{6}=1$
⇒ $t-3= 6$
$\therefore t=9$ days
Hence, the correct answer is 9.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books