Question : A and B can do a piece of work in 10 days and 15 days, respectively. They worked together, but 5 days before the completion of the work, A left. In how many days was the work completed?
Option 1: 4
Option 2: 8
Option 3: 6
Option 4: 9
New: SSC CHSL tier 1 answer key 2024 out | SSC CHSL 2024 Notification PDF
Recommended: How to crack SSC CHSL | SSC CHSL exam guide
Don't Miss: Month-wise Current Affairs | Upcoming government exams
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: 9
Solution : Given: Time taken by A = 10 days Time taken by B = 15 days A left the work 5 days before the completion of the work. Let the total work be 1 unit. ⇒ A's 1 day work = $\frac{1}{10}$ And B's 1 day work = $\frac{1}{15}$ Both (A + B)'s 1 day's work = $\frac{1}{10}+\frac{1}{15}$ = $\frac{3+2}{30}=\frac{5}{30}=\frac{1}{6}$ Let $t$ be the number of days A and B worked together before A left. Now, A left 5 days before the completion of the work ⇒ For $(t-5)$ days, A and B worked together. Work done in $(t-5)$ days = $\frac{1}{6}\times (t-5)$ Work done by B in 5 days = $5\times\frac{1}{15}$ = $\frac{1}{3}$ Now, Work done together in $(t-5)$ days + work done by B alone in 5 days = 1 ⇒ $\frac{1}{6}\times (t-5)+\frac{1}{3}=1$ ⇒ $\frac{t-5+2}{6}=1$ ⇒ $t-3= 6$ $\therefore t=9$ days Hence, the correct answer is 9.
Candidates can download this e-book to give a boost to thier preparation.
Result | Eligibility | Application | Admit Card | Answer Key | Preparation Tips | Cutoff
Question : A can complete a piece of work in 9 days. B and C can complete the same work in 12 days and 18 days respectively. If A, B, and C work together, then in how many days will they complete the work?
Question : A, B, and C can complete a work in 10, 12 and 15 days respectively. A left the work 5 days before the work was completed and B left 2 days after A had left. Number of days required to complete the whole work is:
Question : P, Q, and R can complete a work alone in 12,15, and 20 days respectively. They started the work together. P left the work 8 days before the work was completed and Q left the work 5 days after P had left. R completed the remaining work alone. How many days will be required to
Question : A and B working separately can do a piece of work in 9 and 15 days respectively. If they work on alternate days, starting with A, then the work will be completed in:
Question : 10 women can do a piece of work in 6 days, 6 men can do the same work in 5 days, and 8 children can do it in 10 days. What is the ratio of the efficiency of a woman, a man, and a child, respectively?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile