15 Views

Question : A and B can do a piece of work in 10 days and 15 days, respectively. They worked together, but 5 days before the completion of the work, A left. In how many days was the work completed?

Option 1: 4

Option 2: 8

Option 3: 6

Option 4: 9


Team Careers360 23rd Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 9


Solution : Given: Time taken by A = 10 days
Time taken by B = 15 days
A left the work 5 days before the completion of the work.
Let the total work be 1 unit.
⇒ A's 1 day work = $\frac{1}{10}$
And B's 1 day work = $\frac{1}{15}$
Both (A + B)'s 1 day's work = $\frac{1}{10}+\frac{1}{15}$ = $\frac{3+2}{30}=\frac{5}{30}=\frac{1}{6}$
Let $t$ be the number of days A and B worked together before A left.
Now, A left 5 days before the completion of the work
⇒ For $(t-5)$ days, A and B worked together.
Work done in $(t-5)$ days = $\frac{1}{6}\times (t-5)$
Work done by B in 5 days = $5\times\frac{1}{15}$ = $\frac{1}{3}$
Now, Work done together in $(t-5)$ days + work done by B alone in 5 days = 1
⇒ $\frac{1}{6}\times (t-5)+\frac{1}{3}=1$
⇒ $\frac{t-5+2}{6}=1$
⇒ $t-3= 6$
$\therefore t=9$ days
Hence, the correct answer is 9.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books