2 Views

Question : A and B working separately can complete a piece of work in 10 and 16 days, respectively. If they work for a day alternately, with A beginning the work, in how many day (s) will the work be completed?

Option 1: $10 \frac{1}{4}$

Option 2: $12 \frac{1}{4}$

Option 3: $1\frac{1}{4}$

Option 4: $\frac{1}{4}$


Team Careers360 6th Jan, 2024
Answer (1)
Team Careers360 20th Jan, 2024

Correct Answer: $12 \frac{1}{4}$


Solution : Let the total work be 80 units
The efficiency of A and B = $\frac{80}{10}$ units/day, $\frac{80}{16}$ units/day respectively
⇒ The efficiency of A and B = 8 units/day, 5 units/day respectively
Effective efficiency of A and B together = 8 + 5 = 13 units/day
According to the question,
They work on alternative days.
⇒ Work completed in 2 days = 13 units
In 12 days work completed = 78 units
Now, the remaining 2 units will be completed by A in $\frac{2}{8}$ days or $\frac{1}{4}$ days.
⇒ Total time = $12 + \frac{1}{4}=12\frac{1}{4}$ days
Hence, the correct answer is $12\frac{1}{4}$.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
GRE ® Registrations 2024
Apply
Apply for GRE® Test now & save 10% with ApplyShop Gift Card | World's most used Admission Test for Graduate & Professional Schools
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books