Question : A and B working separately can complete a piece of work in 10 and 16 days, respectively. If they work for a day alternately, with A beginning the work, in how many day (s) will the work be completed?
Option 1: $10 \frac{1}{4}$
Option 2: $12 \frac{1}{4}$
Option 3: $1\frac{1}{4}$
Option 4: $\frac{1}{4}$
Latest: SSC CGL preparation tips to crack the exam
Don't Miss: SSC CGL complete guide
New: Unlock 10% OFF on PTE Academic. Use Code: 'C360SPL10'
Correct Answer: $12 \frac{1}{4}$
Solution : Let the total work be 80 units The efficiency of A and B = $\frac{80}{10}$ units/day, $\frac{80}{16}$ units/day respectively ⇒ The efficiency of A and B = 8 units/day, 5 units/day respectively Effective efficiency of A and B together = 8 + 5 = 13 units/day According to the question, They work on alternative days. ⇒ Work completed in 2 days = 13 units In 12 days work completed = 78 units Now, the remaining 2 units will be completed by A in $\frac{2}{8}$ days or $\frac{1}{4}$ days. ⇒ Total time = $12 + \frac{1}{4}=12\frac{1}{4}$ days Hence, the correct answer is $12\frac{1}{4}$.
Candidates can download this ebook to know all about SSC CGL.
Answer Key | Eligibility | Application | Selection Process | Preparation Tips | Result | Admit Card
Question : A and B can complete a work in 10 and 16 days respectively. A begins to do the work and they work alternatively one at a time for one day each. The whole work will be completed in:
Question : X and Y can complete a work in 9 days and 36 days, respectively. X begins to do the work and they work alternately one at a time for one day each. The whole work will be completed in:
Question : P, Q, and R can complete a piece of work in 9, 12, and 18 days, respectively. Working together, how much work can they complete in one day?
Question : A can do a piece of work in 6 days, working 8 hours a day, while B can do the same work in 4 days, working 10 hours a day. If the work has to be completed in 5 days, how many hours do they need to work together in a day?
Question : A, B, and C can do a piece of work in 30, 20, and 10 days respectively. A is assisted by B on one day and by C on the next day, alternately. How long would the work take to finish?
Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile