6 Views

Question : A and B working separately can complete a piece of work in 10 and 16 days, respectively. If they work for a day alternately, with A beginning the work, in how many day (s) will the work be completed?

Option 1: $10 \frac{1}{4}$

Option 2: $12 \frac{1}{4}$

Option 3: $1\frac{1}{4}$

Option 4: $\frac{1}{4}$


Team Careers360 6th Jan, 2024
Answer (1)
Team Careers360 20th Jan, 2024

Correct Answer: $12 \frac{1}{4}$


Solution : Let the total work be 80 units
The efficiency of A and B = $\frac{80}{10}$ units/day, $\frac{80}{16}$ units/day respectively
⇒ The efficiency of A and B = 8 units/day, 5 units/day respectively
Effective efficiency of A and B together = 8 + 5 = 13 units/day
According to the question,
They work on alternative days.
⇒ Work completed in 2 days = 13 units
In 12 days work completed = 78 units
Now, the remaining 2 units will be completed by A in $\frac{2}{8}$ days or $\frac{1}{4}$ days.
⇒ Total time = $12 + \frac{1}{4}=12\frac{1}{4}$ days
Hence, the correct answer is $12\frac{1}{4}$.

SSC CGL Complete Guide

Candidates can download this ebook to know all about SSC CGL.

Download EBook

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books