20 Views

Question : A and B working separately can do a piece of work in 9 and 15 days respectively. If they work on alternate days, starting with A, then the work will be completed in:

Option 1: 10 days

Option 2: 11 days

Option 3: 9 days

Option 4: 12 days


Team Careers360 24th Jan, 2024
Answer (1)
Team Careers360 25th Jan, 2024

Correct Answer: 11 days


Solution : Given: A and B working separately can do a piece of work in 9 and 15 days respectively. They work on alternate days, starting with A.
Let the total work = LCM of 9 and 15 = 45 units
A’s 1 day work = $\frac{45}{9}$ = 5 units
B’s 1 day work = $\frac{45}{15}$ = 3 units
If they work on alternate days, they will finish (5 + 3) = 8 units of work in 2 days,
In 10 days they will finish (8 × 5) = 40 units of work,
The remaining work = (45 – 40) = 5 units of work, which A can finish on the 11th day.
So, the work will be completed in 11 days.
Hence, the correct answer is 11 days.

How to crack SSC CHSL

Candidates can download this e-book to give a boost to thier preparation.

Download Now

Know More About

Related Questions

TOEFL ® Registrations 2024
Apply
Accepted by more than 11,000 universities in over 150 countries worldwide
Manipal Online M.Com Admissions
Apply
Apply for Online M.Com from Manipal University
View All Application Forms

Download the Careers360 App on your Android phone

Regular exam updates, QnA, Predictors, College Applications & E-books now on your Mobile

150M+ Students
30,000+ Colleges
500+ Exams
1500+ E-books